The most recent ECIA Electronic Component Sales Trends (ECST) survey from September continue to show a clear trend: the overall component index increased from 136.7 in August to 142.0 in September. Every component segment and the end-market measure outperformed expectations. Individual end-market scores range from 104.5 (Consumer Electronics) to 150.0 (Avionics / Military / Space), with all segments above the 100-point growth threshold. Based on material categories:

  • Semiconductors: 77 % of respondents report increasing lead time pressure (up from 72 % in August) – the trend is worsening, not stabilising
  • Passives and Electro-Mechanical / Connectors: 61–63 % report increasing pressure, with zero respondents reporting declining pressure

The report's conclusion is unambiguous: demand sentiment remains strongly positive across all end-markets, with supply pressures continuing to deepen in semiconductors and remain broadly elevated across all other component categories.

 

Component Market – General Lead Time & Price Overview

European B2B distributor bookings for Q2 2026 averaged book-to-bill of 1.40, with year-to-date bookings up +58 % vs. 2025, as based on the TTI Q4 2026 Market Update. On the other hand, the Euro PMI for Q3 reached 52.9 – the highest level since 2022. Strong demand signals are, however, running into a progressively tightening supply base.

The Supplyframe Commodity IQ All-Component Inventory Index stood at 43.7 in August 2026 — representing the 34th consecutive month of year-on-year contraction since December 2023, with the index projected to reach a new five-year low in September; a clear signal the amount of available inventory is diminishing and on the lowest levels since years.

A Global Electronics Association survey conducted in Q3 2026 found that 64 % of electronics manufacturers reported limited availability and extended lead times; 0 % reported excess supply.

The table below provides a cross-category overview of current lead time ranges and price trend direction. These ranges reflect the general view; specific part numbers and automotive-grade variants often exceed the upper bounds shown.

 

Component Category

Lead Time Range (weeks)

Trend

Price Direction

Microcontrollers (MCU)

30–55+

Worsening ↑

Increasing

Memory (DRAM / NAND / eMMC)

26–52

Tightening ↑

Increasing (+40–70 %)

FPGAs / CPLDs

40–52

Stable

Stable–mild increase

Power semiconductors & analog ICs

26–40

Worsening ↑

Increasing

Discretes (MOSFETs, IGBTs, diodes)

15–52

Worsening ↑

Increasing

MLCCs & passives (high-capacitance)

12–45

Tightening ↑

Increasing

Standard resistors & inductors

10–28

Stable

Mild increase

Connectors & interconnect

8–32

Stable

Increasing

PCB laminates (standard FR-4)

8-12

Worsening ↑

Sharply increasing

PCB laminates (high-speed / HDI)

20+

Critical ↑

Sharply increasing

 

AI-driven demand continues to absorb premium capacity and crowding out supply for standard industrial and consumer products. Manufacturers serving AI data centre, EV, and advanced networking end-markets face the sharpest allocation constraints, while demand for standard consumer-grade parts remains better-supplied.

PCB Laminates & Substrates

Pricing

The PCB base material shortage flagged in our recent alert has continued to intensify. CCL and prepreg prices have risen through multiple consecutive rounds throughout 2025–2026, driven by three converging input cost pressures: copper (the dominant input, representing 30–50 % of CCL cost depending on board type and copper weight), epoxy resin, and glass fabric. All three remain at or near historic highs. The pace and scale of increases has been exceptional – unprecedented what has been seen in the past on this commodity. We continue to observe further increases.

Availability

What has changed materially since Q3 is the nature and scope of the availability constraint. The shortage, previously concentrated in advanced laminates, has now spread to standard FR-4. The shift – confirmed by NCAB Group and Würth Elektronik – affects a far broader range of laminate types.

Current approximate lead times by laminate type:

  • Standard FR-4: 8-12 weeks – supply currently adequate but prices are volatile and further increases signalled
  • High-Tg / HDI : 20–28 weeks – under allocation constraints; previously stocked items now require lead time
  • Advanced low-loss / HVLP grades: up to 26 weeks (~6 months) –allocated to priority AI and data centre programmes;

We observe more often thedelivery periods for advanced PCB’s reaching even 6 months. This is not a transient disruption: it reflects structural capacity constraints in both glass fabric and copper foil production that cannot be resolved in the short term. There is a real constraint in availability of base materials. Spot stock of prepreg in open-market channels is exhausted; PCB manufacturers without secured allocation agreements are experiencing production delays.

Quote validity has shortened from 30 days to 5–7 days. From one of our suppliers, we hear unofficial signals that factories will start to extend the offer validity to approximately 2-3 weeks, which could mean a higher level of stability from both price and lead time perspective, yet it is not confirmed in real circumstances. Other suppliers, deny such tendency.

Chinese New Year 2027

Chinese New Year 2027 falls from 6th February until 20th of February. In practice, the effective production shutdown is longer with realistic total disruption window for deliveries throughout the whole February. With shipping time added, the first reliable deliveries from Chinese PCB/material suppliers following CNY are not expected before the latter part of the second half of March 2027. Given current lead times, orders placed in November/December or later will be competing for very limited pre-holiday capacity or will fall entirely into the post-CNY queue, with realistic delivery no earlier than late March or April 2027.

Semiconductors, Passives & Connectors


Electronics component lead times are now broadly elevated across all major families — a trend confirmed consistently across Q3/Q4 2026 industry surveys and our own procurement observations.

Price increases and extending lead times remain the dominant theme. The following table summarises the most significant manufacturer actions confirmed since our previous alert, while we expect further notifications of increases to take effect in January 2027.

 

Manufacturer

Action / Development

Effective date

NXP Semiconductors

3rd price adjustment notice in 2026. Affected: automotive processors, MCUs, Bluetooth & NearLink multi-mode wireless. Drivers: raw materials, energy, labor, logistics, upstream vendor costs.

1 January 2027

onsemi

Price increase formally announced across portfolio.

10 October 2026

Renesas Electronics

Price increase covering R-Car and RH850 MCU series.

1 January 2027

STMicroelectronics

Four consecutive increase within the last 12 months

1 January 2027

TSMC

Mature-node wafer price increase planned; further cost pressure on all fabless suppliers' portfolios.

Early 2027

Analog Devices (ADI)

Lead times 60–70 weeks; delivery commitments extend into 2028.

Lead time

Texas Instruments

Real distributor lead times 30–52 weeks on automotive/industrial analog; significantly exceeds official stated manufacturer lead times.

Lead time

AMD / Xilinx FPGAs

Lead times 40–70 weeks across product families; no improvement trend visible.

Lead time

Microchip

Official lead times have form one day to another shifted from 10-12 weeks to 42 weeks.

Lead time

 

Passives: high-capacitance MLCCs remain the tightest segment, with lead times of 25–45 weeks. Samsung has closed its order book on selected AI-grade items; Murata has issued withdrawal notices on multiple commercial series with no like-for-like replacement. Tantalum and polymer electrolytic capacitors follow at 30–50 weeks; resistors and inductors broadly 10–29 weeks, with specialty types under growing pressure. Yageo implemented increases of up to 50 % on capacitor lines and 15–20 % on resistors during 2026.

Connectors: pricing continues to rise, driven primarily by copper cost escalation. HARTING implemented +8.6 % on the Han industrial connector range effective 9 October 2026. Lead times remain comparatively stable at 8–32 weeks across most connector families (Molex, Amphenol, TE Connectivity, ITT), but further pricing rounds are expected in 2027.

Please, keep in mind that in most cases the official lead times do not represent the realistic lead time, with realistic being extended. Do not plan strictly based on official lead times.
 

Price Increases Apply to Existing Confirmed Backlog (Open Orders)


As informed on numerous occasions previously - the pattern remains unchanged: price increases continue to be applied to existing confirmed backlog, not only to new orders. With the enormous scale of price increases, as well as their frequency, matched with increasing lead times - please be aware that is becoming more and more inevitable that prices on open orders will change before delivery.

Commodity Prices & Transportation


Below key commodity moves year-on-year, as well as a 2-year change (in brackets), to show the perspective of a longer term trend.

  • Copper: + 30% YoY (50% 2Y) – drives PCB laminate, connector and capacitor electrode costs
  • Tin: + 30% YoY (60% 2Y) - drives up the cost of PCBA consumables.
  • Silver: +10 % YoY (30% 2Y) – impacts MLCC electrode paste and contact materials
  • Lithium: +12 % YoY(20% 2Y) – affects battery cells and electrolytic capacitor production
  • Steel: +27 % YoY(75% 2Y) – enclosures, relay frames, connector housings
  • Crude Oil (Brent): +55 % YoY (37% 2Y) – plastics, transportation

Ocean freight rates (FBX11) changed 57% YoY, while Air freight costs rose 30% since the beginning of the year as based on Freightos. Both refer to Asia - Northern Europe route.
 

Outlook & Projections for 2027


The consensus among many industry analysts entering 2027 is clear: this is a structural shift, not a cyclical correction. The component market tightening that intensified from Q4 2025 is not expected to suddenly self-correct shortly. What makes this cycle fundamentally different is that the demand driving it comes from genuinely new markets — AI infrastructure and data centre build-out, and a generational increase in aerospace and defence spend (drones, low-Earth-orbit satellites, autonomous systems) — that did not exist at this scale. These are not established markets running temporarily hot; they are structural growth areas adding net-new demand on top of everything that was already there and will not unwind from one day to another. Many industry executives describe this as a trend and are planning for continued pressure through at least 2027–2028, and for key categories such as memory through 2030.

Broader supply chain view
A distinguishing feature of the current cycle, compared to previous shortages, is that constraints extend multiple tiers below the finished component. Choke points increasingly sit at the suppliers to suppliers, not at the manufacturer itself. Raw material bottlenecks are a concrete example: copper is under growing pressure as demand across electronics, power infrastructure, and EV applications converges; high-purity process gases are similarly constrained; glass fibre feedstocks for PCB laminates face structural capacity limits for years ahead. Fewer manufacturers are capable of producing the enabling technologies driving today's growth, which means there is less substitution flexibility when a constraint appears anywhere in the chain.

Geopolitical risks remain high
The one remaining variable that cannot be planned for is geopolitical and trade policy: escalating restrictions could trigger unplanned supply disruptions with little warning, while sudden trade barriers could equally suppress demand and restructure supply chains at short notice causing major disruptions. Neither outcome can be timed or priced in advance — which makes geopolitical risk the primary wild card for 2027 planning.

Lessons from post - COVID era
One important nuance is that a portion of current market demand is surely driven by precautionary ordering rather than immediate production need — a pattern recognisable from the COVID period, which moved the industry from just-in-time through just-in-case and ultimately to just-too-much. The same fear-of-shortage dynamic is naturally present today, particularly in segments closest to the AI build-out. Thus, we encourage to plan your procurement on the basis of actual production schedules and realistic forecasts, not on market anxiety. The risk of over-ordering exists, but the risk of under-planning is greater — because lead times are long regardless of whether the demand picture eventually normalises. In conclusion: plan based on demand, not fear, but do plan ahead as lead times are extended.

Planning ahead
The direct consequence is that component availability is increasingly determined by who planned ahead, not who needs parts most urgently. AI and defence customers are committing capital directly with manufacturers to secure future capacity, effectively crowding out standard industrial buyers from available allocations. The procurement model has shifted: delivery assurance and confirmed backlog now determine supply access more than price. Customers who do not extend their planning horizons and wait with decisions will face the same exposure as in 2020–2022 — shortages and cost increases arriving simultaneously, with limited options once the window closes.

From one of our PCB distributors, we do get early signals that the offer validity will extend for the specific commodity, yet this is rather an early signal of higher stability not “back to normal”. On the contrary, other PCB suppliers od not confirm such trend.

Summary

The electronic components market remains tight across all key categories, with extended lead times, rising prices — including on already confirmed orders — and shrinking availability on the open market. The approaching Chinese New Year will be an additional factor limiting deliveries in the first quarter of 2027. Most component categories continue to deteriorate, and no clear improvement in market conditions is currently visible.

CONTACT

LET US WORK TOGETHER!

Benefit from our expertise in electronics manufacturing, today!
Let us learn your problems and requirements, and we will propose a business model that is most suitable for you.

Fundusze Europejskie, Rzeczpospolita Polska, Unia Europejska
Made by Web24